Council Works Report 7 October 2022

Civil Infrastructure Works for the week ending 7 October 2022

  • Complete stabilising Hawthorne Drive
  • Commence stabilising Northeys Road
  • Commence installing new pipes on Bindawalla Road
  • Complete gravel patching flood damage on Allinghams Road, Dalveen Road, Looagona Road, Danehurst Road
  • Commence gravel patching Athol Road
  • Complete drainage work using contractor Blue Mountain Road
  • Commence drainage works using contractor Hillview Road
  • Continue mowing in Uralla and Bundarra
  • Continue weed spraying in Uralla and Bundarra
  • Continue tar patching on regional roads

Northeys-Road.png

Northeys Road finalisation of the pavement stabilisation for sealing, weather permitting next week.

Works scheduled next week, commencing 10 October 2022

  • Complete stabilising Northeys Road
  • Continue installing new pipes Bindawalla Road
  • Commence heavy patch Mount Drummond Road
  • Complete gravel patching and grading Athol Road
  • Commence grading Kingstown/Bendemeer Road
  • Complete drainage works using contractor Hillview Road
  • Continue mowing in Uralla and Bundarra
  • Continue weed spraying in Uralla and Bundarra

Rural-Road-Maintenence.jpg