Council Works Report 4 March 2022

Civil Infrastructure Works for the week ending 4 March 2022

  • Continue sub grade and boxing out shoulders on Tolleys Gully Construction
  • Continue final on Bergen Road Construction ready for sealing on Friday or Monday pending on weather
  • Complete grading Collomendy Road
  • Commence grading Johnsons Road
  • Complete grading Warrembah Road
  • Commence grading Box Forrest Road
  • Continue tar patching MR124 and MR73 rural roads
  • Reseal Bundarra Urban Streets:
    • Darby Street
    • Court Street
    • Bowline Street
    • Dawkins Street
  • Complete Resealing
    • Rocky River Road
    • Rowan Avenue in Uralla
  • Complete slashing Rocky River and Terrible Vale Roads ready for reseals
  • Continue mowing in Uralla and Bundarra recreation areas

Works scheduled next week, commencing 7 March 2022

  • Complete resealing Terrible Vale Road
  • Continue sub grade and boxing out on Tolleys Gully Construction
  • Complete Bergen Road construction (except for the guard rail it should be installed on the 14/3/22)
  • Complete grading Johnsons Road
  • Complete grading Box Forrest Road
  • Commence grading and graveling washed out areas on Traceys Loop Road
  • Commence grading Borges Road
  • Continue slashing where needed
  • Continue mowing and weed spraying in Uralla and Bundarra
  • Continue whipper snipping guard rails on bridges on regional and rural roads