Council Works Report 30 July 2021

Civil Infrastructure Works for the week ending 30 July 2021

  • Completed gravel re-sheeting Bullens Road
  • Completed gravel re-sheeting Yellow Box Drive
  • Completed gravel patching Rosehill Road
  • Completed grading Traceys Loop/Road
  • Completed grading Clerks Road
  • Completed Goldfinch Street
  • Completed grading Retreat Road
  • Commenced Baldersleigh Road
  • Commenced grading Old Wollun Road
  • Continued tar patching on rural Roads
  • Continued street furniture refurbishment
  • Continued sign maintenance in Uralla and rural Roads

Rural-Road-Maintenence.jpg

Works scheduled next week, commencing 2 August 2021

  • Continue tar patching on rural and regional roads
  • Continue drainage in Uralla and rural roads
  • Continue street furniture refurbishment
  • Continue multipurpose sports courts Bundarra
  • Commence Tolleys Gully Bridge Abutments
  • Re-commence Hawthorne Drive Construction Stage 1
  • Commence grading Borgers Road
  • Commence grading Glenburnie Road
  • Commence pavement repairs on Invergowrie Road near Invergowrie store