Council Works Report 28 July 2022

Civil Infrastructure Works for the week ending 28 July 2022

  • Continue sub grade and boxing out last 200m on Hawthorne Drive Construction (see photo below)
  • Complete grading Barraba Road
  • Complete grading Worthington Street
  • Complete grading Target Hill Road
  • Complete grading Mihi Road and spot graveling
  • Commence grading Lindfield Road
  • Continue tar patching MR73 Central
  • Complete tar patching Arding Road
  • Continue drainage on rural roads
  • Continue sign maintenance in town and rural roads

Hawthorne-Drive-Construction.jpg

Works scheduled next week, commencing 1 August 2022

  • Complete sub grade on Hawthorne Drive Construction ready for stabilising
  • Commence grading Bakers Creek Road
  • Continue grading Lindfield Road
  • Commence grading Dwyers Range Road
  • Continue tar patching MR73 Central
  • Commence tar patching Mount Butler Road
  • Continue drainage on rural roads
  • Continue sign maintenance on rural roads and in town
  • Commence patching on rural unsealed roads (dependent on staff numbers)

 