Council Works Report 27 May 2022

Civil Infrastructure Works for the week ending 27 May 2022

  • Completed tree clearing and started drainage works ready for boxing out shoulders on Hawthorne Drive Construction (see photo)
  • Continued grading Hillview Road
  • Continued grading Old Kingstown Road
  • Completed grading Mount Butler Road
  • Completed grading Wilkinsons Road
  • Completed grading Vale View Road
  • Commenced grading Rosehill Road
  • Continued setting out school crossings at Bundarra
  • Continued tar patching on rural roads
  • Continued mowing in Uralla and Bundarra
  • Completed trimming hedges at the Old Cemetery
  • Completed remarking sporting fields ready for school carnivals
  • Continued water meter readings in Uralla and Bundarra
  • Continued weeding kerb blisters
  • Continued sign maintenance on rural roads and in Uralla

Hawthorne-Drive-Construction.jpg

 

Works scheduled next week, commencing 30 May 2022

  • Continue drainage works and start graveling shoulders on Hawthorne Drive Construction
  • Continue grading Hillview Road
  • Commence grading Hardens Road
  • Complete grading Rosehill Road
  • Continue tar patching rural roads
  • Continue mowing in Uralla and Bundarra
  • Continue drainage in Uralla and rural roads
  • Continue weeding kerb blisters
  • Continue sign maintenance on rural roads and in Uralla
  • Complete school crossings at Bundarra (see photo) except for asphalt overlay – by contractor

 

Bundarra-School-Crossing.jpg