Council Works Report 24 September 2021

Civil Infrastructure Works for the week ending 24 September 2021

  • Completed grading Goldsworth Road
  • Completed grading Rowbottoms Road
  • Completed grading Maitland Point Road
  • Completed grading Gostwyck Road
  • Completed grading Sanctuary Drive
  • Commenced grading Lindon Road
  • Commenced grading Hillview Road
  • Commenced grading Gap Road
  • Continued sign maintenance in Uralla and on rural roads
  • Continued drainage maintenance in Uralla and rural roads
  • Continued with Tolleys Gully Bridge abutments (see photo)
  • Repaired water damaged pavement on Thunderbolt Way at Yarrowyck
  • Continued tar patching regional and rural roads
  • Commenced mowing Uralla footpaths and parks
  • Revisited Rocky River School turning bay for further drainage works (see photo)

Works scheduled next week, commencing 27 September 2021

  • Continue tar patching on rural and regional roads
  • Continue drainage in Uralla and rural roads
  • Continue Tolleys Gully Bridge abutments
  • Continue mowing in Uralla town area
  • Commence grading Carlon-Menzies Road
  • Commence grading Athol Road 