Council Works Report 2 September 2022

Civil Infrastructure Works for the week ending 2 September 2022

  • Complete grading Dog Trap Road
  • Complete grading Bakers Creek Road
  • Commence grading Georges Creek Road
  • Complete grading Budumba Road
  • Complete grading Baker Road
  • Complete grading Kalinda Road
  • Complete grading Adina Road
  • Complete grading Kooda Road
  • Complete grading Lentara Road
  • Complete grading Kareela Road
  • Complete grading Moffatt Road
  • Complete grading Malapatinti Road
  • Complete grading Brentara Road
  • Complete grading Barloo Road
  • Commence spot graveling Pansyfield and Primrose Roads
  • Patch gravel washouts on Danehurst and Balala Roads
  • Continue tar patching Dumaresq Road
  • Continue tar patching on regional Roads
  • Commenced kerb and gutter in Roman Street (see photos)
  • Commence mowing and weed spraying in Uralla and Bundarra
  • Continue street furniture refurbishing in main street
  • Continue footpath kerb and gutter maintenance in Uralla

Works scheduled next week, commencing 5 September 2022

  • Complete spot gravelingon Primrose and Pansyfield Roads
  • Commence grading Lawson Road
  • Commence grading Yellowbox Road
  • Commence grading Ferris Lane
  • Continue grading Devoncourt Road
  • Commence grading Athol Road
  • Complete grading Georges Creek Road
  • Commence grading Clerks Creek Road
  • Commence grading Baldersleigh Road
  • Continue tar patching Invergowrie area
  • Continue tar patching regional roads
  • Continue refurbishing seats in main street
  • Continue mowing in Uralla and Bundarra
  • Continue weed spraying in Uralla and Bundarra

 