Council Works Report 18 June 2021

Civil Infrastructure Works for the week ending 18 June 2021

  • Grading Spring Gully Road
  • Grading Bakers Creek Road
  • Gravelling Hillview Road
  • Continued shared footpath in Plane Avenue (see photo)
  • Continued tar patching on rural roads
  • Ceased Hawthorne Drive Construction (due to wet weather)
  • Cleaned sediment traps and drains in town
  • Commenced winning gravel for Bendemeer Road

     

    Works scheduled next week, commencing 21 June 2021

    • Rural-Road-Maintenence.jpg Commence Balala Road gravel resheeting
    • Commence grading Martins Lane
    • Commence grading Haynes Lane
    • Commence grading Dorlie Lane
    • Continue grading Bakers Creek Road
    • Recommence Hawthorne Drive Construction
    • Continue winning gravel for Bendemeer Road
    • Continue Plane Avenue shared footpath
    • Continue tar patching regional roads
    • Commence street furniture refurbishment
    • Continue drainage in town and rural roads