Council Works Report 17 June 2022

Civil Infrastructure Works for the week ending 17 June 2022

  • Completed drainage ready for boxing out shoulders on Hawthorne Drive
  • Commenced gravelling shoulders Hawthorne Drive
  • Completed gravel patching Northeys Road
  • Continued grading Hillview Road
  • Commenced grading Blue Mountain Road
  • Commenced school crossing Wood Street Uralla (see photo)
  • Commenced Park Street school crossing
  • Continued tar patching on rural and regional Roads
  • Commenced Alma Park garden maintenance
  • Completed Fuller Park upgrade shelters and tables
  • Continued sign maintenance rural and regional roads
  • Continued drainage rural roads
  • Commenced heavy patching Arding Road by contractors. Incorporation of the lime with the gravel overlay. (see photo)

Works scheduled next week, commencing 20 June 2022

  • Continue boxing out and gravelling shoulders Hawthorne Drive
  • Commence Gills Road grading
  • Complete Mount Drummond Road
  • Commence Ross Road grading
  • Continue tar patching rural and regional roads
  • Continue Park Street school crossing
  • Continue Alma Park maintenance
  • Continue kerb blister maintenance
  • Commence cleaning storm damage Alma Park
  • Continue cleaning kerb and gutters
  • Heavy patching on Kliendienst Road by contractors.