Council Works Report 16 July 2021

Civil Infrastructure Works for the week ending 16 July 2021

Wet weather and associated wet ground conditions have limited progress this week.

  • Continued gravel re-sheeting Bendemeer Road
  • Rural-Road-Maintenence.jpg Continued gravel re-sheeting Barraba Road
  • Completed grading Bakers Creek Road
  • Continued all concrete work on footpath/cycleway in Plane Avenue
  • Continued tar patching on rural roads
  • Continued street furniture refurbishment
  • Continued sign maintenance in Uralla and rural Roads
  • Continued erecting equipment at Bundarra multipurpose courts
  • Completed grading Brechts Lane
  • Completed grading Plug Street
  • Completed grading Warrembah Road
  • Completed grading Georges Creek Road

 

Works scheduled next week, commencing 19 July 2021

  • Complete gravel re-sheeting Bendemeer Road
  • Complete gravel re-sheeting Barraba Road
  • Continue tar patching on rural and regional Road
  • Complete topsoiling and seeding shared footpath Plane Avenue
  • Continue drainage in Uralla and rural Roads
  • Continue Street furniture refurbishment
  • Continue multipurpose sports courts Bundarra
  • Commence grading Clerks Road
  • Commence grading Baldersleigh Road
  • Commence grading Bundarra local/urban roads
  • Commence grading Westvale Road
  • Commence grading Jobsons Lane
  • Commence grading Mabbots Lane
  • Commence grading Retreat Road
  • Commence tree clearing and drainage for stage 2 along Hawthorne Drive
  • Commence pavement repairs on Invergowrie Road near Invergowrie Store