Council Works Report 14 October 2022

Civil Infrastructure Works for the week ending 14 October 2022

  • Complete stabilizing Northeys Road
  • Commence final trim on Northeys Road ready for sealing
  • Complete heavy patch Mt Drummond Road
  • Commence heavy patch Baldersleigh Road
  • Complete gravel patch and grading Athol Road
  • Commence grading Kingstown/Bendemeer Road
  • Complete rural road flood damage repairs in Bundarra area
  • Continue drainage works using contractor Hillview Road
  • Continue tar patching regional roads
  • Continue mowing In Uralla and Bundarra
  • Continue weed spraying in Uralla and Bundarra

Planned works next week, commencing 17 October 2022

  • Complete final trim on Northeys Road
  • Commence heavy patch Noalimba Avenue
  • Commence Tolleys Gully construction
  • Complete heavy patch Baldersleigh Road
  • Commence heavy patch Barraba Road
  • Recommence grading Baldersleigh Road
  • Continue installing new pipes Bindawalla Road
  • Continue grading Kingstown/Bendemeer Road
  • Complete drainage works using contractor Hillview Road
  • Continue tar patching regional roads
  • Continue mowing in Uralla and Bundarra
  • Continue weed spraying Uralla and Bundarra

 